PGPL to try flowing gas through 2nd LNG terminal today

ISLAMABAD: Pakistan GasPort, the country’s second liquefied natural gas (LNG) import terminal, plans to try injecting gas back into the facility’s onshore system on Thursday after a leak forced a shutdown last week, two sources said.

The newly inaugurated terminal suspended operations last week following a gas leak in the insulation joint linking the facility to the connecting pipeline infrastructure.

Since then three gas leaks in total had been found, delaying repair work at the facility, a Pakistan-based industry source said.

A senior Pakistani official said he expects LNG stored inside the floating storage and regasification unit to begin to be converted into gas and injected into the onshore system on Thursday, Dec. 14.

The industry source confirmed this.

On Wednesday, the 138,000 cubic metre capacity Al Jassasiya LNG vessel berthed alongside the GasPort terminal, according to ship-tracking data. Data shows the vessel is carrying cargo.

Industry and trade sources said at least two LNG tankers have been cancelled or diverted away from the terminal since the leak.

Pakistan GasPort owner Associated Group (AG) did not respond to an emailed request for comment. AG’s chairman Iqbal Ahmed is also chairman of Pakistan GasPort.

Must Read

PM for ensuring third party validation in all government procurements

ISLAMABAD: Prime Minister Muhammad Shehbaz Sharif on Thursday directed the relevant authorities to ensure third party validation including quality insurance in all the government procurements. Chairing a...