Balloki Power Plant starts operations

Balloki Power Plant can add up to 1,230 megawatts to the national grid, the equivalent power needed to supply up to 2.5 million Pakistani homes.

ISLAMABAD: Balloki, the third RLNG based power plant has successfully passed all tests and operations have officially started.

The power plant was operationalised by the National Power Parks Management Company Limited (NPPMCL), Harbin Electric International Company Limited (HEI) and GE (NYSE: GE) after the completion of the Balloki power plant, following the successful conclusion of all commissioning works and performance-related tests.

NPPMCL’s CEO Rashid Mahmood said, “I am proud to announce that the Balloki project is now able to supply up to 1,223 megawatts (MW) of uninterrupted power to the national grid, the equivalent electricity needed to supply up to 2.5 million Pakistani homes. This is the second regasified liquefied natural gas (RLNG) power project developed by NPPMCL, the first being the Haveli Bahadur Shah (HBS) power plant, which entered full-fledged combined cycle commercial operations in May 2018. Together, the HBS and Balloki plants have already added over 5.5 billion kilowatt hours of power to the national grid while in the commissioning phase and they will continue to deliver efficient, low cost power for up to 30 years, making a meaningful difference in the lives of the people of Pakistan.”

The contract to set up the plant was awarded by NPPMCL to HEI, which is the engineering, procurement and construction (EPC) contractor for the project and responsible for its installation works and commissioning schedule. HEI sub-contracted GE to supply two of its HA gas turbines, some auxiliary equipment and technical advisory services, The plant had earlier realized an impressive milestone by synchronizing an HA unit to the grid just 74 days after it was delivered to the project site, the shortest duration in which GE’s HA technology has achieved this milestone anywhere in the world.

“The successful completion of Balloki power plant underlines the strong collaboration among NPPMCL, HEI and GE in driving the commissioning of the project. People from more than 25 countries came together to work on this project. Together, we brought the world’s best to power Pakistan – local project management with Chinese engineering expertise and power generation technologies that were developed by advanced research and development teams based in North America and Europe,” added HEI’s Chief Operation Officer and General Director of first Power Division, Li Chao.

GE’s HA technology has now helped to deliver two world records – one for powering the world’s most efficient combined-cycle power plant, based on achieving 63.08 percent gross efficiency at Chubu Electric Nishi-Nagoya Power Plant Block-1 in Japan and another for helping EDF’s Bouchain Power Plant achieve 62.22 percent net combined cycle efficiency in France. It has thus been recognized for record-setting efficiency in both 60 hertz and 50 hertz markets. Balloki is the third RLNG project equipped with GE’s HA technology to reach completion in Pakistan, following the Haveli Bahadur Shah and Bhikki power plants. The three facilities are among the most efficient combined cycle power plants in the world today, adding a total of up to 3,600 MW to Pakistan’s national grid. Efficiency matters as each point of efficiency can generate up to $50 million of fuel savings over 10 years for a 1,000 MW power plant.

Must Read