Stocktaking of power sector challenges in NEPRA State of Industry Report

NEPRA released its State of Industry Report 2022 (SIR) on 30th September, 2022. This year’s addition is particularly significant due to multiple key events that took place in FY 2022, including launch of CTBCM, revised IGCEP, and exorbitant increase in consumer end tariff of electricity. Even though global fuel prices have been the main driver of these excessive increases in cost of electricity, it is ultimately sub-standard and inconsistent planning along with other convoluted issues that lead to a financially stressed power sector. One must applaud the NEPRA for its transparency in highlighting most of the critical challenges that have led to the current abysmal performance of the power sector. This piece is an effort to take stock of all the major issues included in the report.

Following are the key major issues highlighted in the report that have led to an adverse impact on the power sector:

Violation of Economic Merit Order (EMO)

The electricity dispatch in the centralised national grid of Pakistan is based on the Economic Merit Order (EMO) – a key document that ranks the cheapest power plants to run on a daily basis. Several deviations were witnessed in actual dispatch compared to EMO in the past year due to several reasons including i) Shortage of fuel for RLNG plants, ii) System constraints, and iii) Underutilization/non-utilisation of efficient power plants. The combined impact of these violations resulted in an impact of Rs 23.26 billion in FY 2022.

Operation of power plants are partial load

Thermal power plants operating at partial load have lower efficiencies. In Pakistan, the PPAs with IPPs are negotiated as such, that the power purchaser i.e CPPA is liable to pay Part Load Adjustment Charges (PLAC) if the power plant is operated at partial load due to non-evacuation of electricity. Total amount accrued to date in terms of PLAC is Rs 41.74 billion, out of which Rs 23.03 billion were accrued in FY 2022 only. 

Operation of Combined Cycle Power Plants (CCPP) in open cycle mode

Combined cycle power plants (plants operating on gas as well as steam turbines) have higher efficiencies than conventional power plants. However, the tariff is 50% higher, if it is operated in open cycle mode i.e only the gas turbine is operational. In FY 2022, the operation of TPS Guddu (old and 747 MW) in open cycle mode led to a financial impact of more than Rs 55 billion. 

Capacity Payments

Most of our thermal power plants are based on ‘Take or Pay’ contract – meaning that the electricity sale is accompanied by a Capacity Payment component, even if the plants remain un-operational for the whole year.  The total capacity payments in FY 2022 reached a staggering amount of Rs 721 billion. Key reasons for high capacity payments in FY 2022 include: i) low utilisation factor of thermal power plants i.e. 46% (per unit capacity payment go as high as Rs/kWh 18.94 for Hub Power), ii) low utilisation factor of WAPDA hydro power plants i.e. 39% (hydrological risk is mostly borne by power purchaser)

Non-Project Missed Volume

Paying for non-utilisation of power plants is not only the characteristics of thermal power plants. Instead, renewable power plants are also liable to pay Non-Project Missed Volume (NPMV) i.e., payment in case of non-evacuation of available power. This is due to the ‘Must run’ status of renewable energy power plants. Although these are charged to DISCOs and NTDC (not passed through to consumers), the ultimate price is paid by the public due to its contribution to DISCO losses leading to circular debt. In FY 2022, payments on account of NPMV claimed was Rs 1.17 billion.

Liquidated Damages

The government procures new power projects to replace the current expensive fleet of power generators with low-cost power projects. However, delay in commissioning of these plants or their unavailability can result in imposition of Liquidated Damages on generators by the power purchaser. Two issues exist in this regard: i) Current LDs are not rationalised to reflect the true cost of the financial impact due to unavailability of low-cost power, ii) CPPA-G usually compromise on LDs claims due to high accrued payable to corresponding IPPs.

Delays in Distributive energy projects

Several distributive energy projects could lower the cost of CPPA basket by procuring energy at lower tariff from distributive energy power plants like solar and bagasse based power generators. However, due to delay tactics adopted by DISCOs, the opportunity loss of procuring electricity from these distributive sources added up to Rs 1.8 billion in the past two years.

 

Losses in transmission system

Losses in the transmission system of electricity directly impact the end consumer tariff. Losses by NTDC in FY 2022 stands at 2.63% which is higher than the allowable limit of 2.5%. The additional 3,696 units that had to be produced due to higher than allowable losses, resulted in a financial loss of Rs 72 billion. 

Losses in distribution system

Like transmission, the distribution network losses also exceed the allowable limit by NEPRA. In FY 2022, the average distribution losses for DISCOs were 17.13% as compared to allowable limit of 13.41%. This resulted in a financial impact of Rs 113 billion. Additionally, NEPRA in its determinations assumes the 100% recoveries by DISCOs against the billed amount to consumers. In reality, the recoveries by DISCOs are lower. In FY 2022, DISCOs were able to recover 90.51% against the billed amount, hence incurring a loss of Rs 230 billion. Both of these technical losses over allowable limits and low recoveries lead to circular debt. As on 30th June 2022, total receivables of all DISCOs stood at Rs 1,498 billion

The report highlights several other issues including; i) Low pressure gas supply to cheaper power plants, ii) Lack of optimisation between the CPPA and KE system, ii) issues related to fuel supply management and procurement, iii) Increase in imported fuel prices, iv) Front loaded debt in IPP’s tariff, v) Right of Way issues for power projects and more. These can be read about in detail from SIR 2022, uploaded on the NEPRA website.

 

 

Basit Ghauri
Basit Ghauri
Basit is a senior associate at ‘Resources Future’ - a private sector energy consultancy. He has extensive expertise in renewable energy systems, sustainable development energy policy, and electricity market. With over four years of experience in the sustainable energy domain, Masters in Sustainable Energy Engineering as Fulbright alumni, and Climate Corps Fellow for Environmental Defense Fund-US, he has led initiatives in project development, feasibility studies, sector diagnostics, diagnostics, and market analysis for various public-private, and development sector institutions.

6 COMMENTS

    • I don’t know what for this regulatory authority is? It has not stopped giving free units to Wapda employees and privileged class. Always putting burden on poor and middle class. Couldn’t stop theft, Couldn’t regulate any activity of discos except announcing price hike. Strange enough, it buy electricity from people producing solar energy at a cheaper rate than it is selling to them. This is utmost violation of law and will be a set back to power production in future. It seems this body wants to squeeze every drop of blood to feed the stranger

  1. Only solution to get rid of power sector losses, electricity shortfall is switching to solar energy. We need to follow the model of developed countries – in order to maintain energy consumption and production balanced. Without taking bold steps, electricity shortfall couldn’t be reduced. Day be day, the burden on middle families pushing them hand to mouth in miserable condition.
    The most funniest point is FPA – it’s like making payments even for the previous months. Even Govt. can’t subsidize on it. The most common point higher authorities must understand is – overbilling and price increasing is not ultimate solution.

  2. Very well explained. Lack of competition amoung the DISCO’s and delay in concieving energy projects seems to be the main reason behind this shortcoming. Monthly increase in tariffs have greatly impact the opinions of masses against the regulatory bodies and the government. Sub-quality planning cannot be shadowed by international fuel prices.

  3. Excellent explanation. The main cause for this weakness appears to be a lack of competition among DISCOs and a delay in developing energy projects. Tariff increases on a monthly basis have had a significant impact on public opinion against regulatory organisations and the government. International fuel prices cannot be used to justify poor planning.

  4. Welcome to Versatile Coupons, the final location for getting a versatile deal on your internet-based buys. Our central goal is to assist customers with enjoying you find the best arrangements and limits on the items you love. We comprehend that setting aside cash can be intense, particularly while shopping on the web. That is the reason we’ve made it our objective to present to you the best-in-class coupons and markdown codes from top retailers. Whether you’re looking for garments, gadgets, or home merchandise, we take care of you.

Comments are closed.

Must Read