ISLAMABAD: Kot Addu Power Company Limited (PSX: KAPCO) successfully completed its Initial Tested Capacity and Initial Heat Rate Test on September 12, 2025.
The tests were conducted under the Tripartite Power Purchase Agreement (TPPA) with Central Power Purchasing Agency (Guarantee) Limited and the National Grid Company of Pakistan Limited. The Independent Engineer issued the Capacity/Heat Rate Test Certificate, establishing September 13, 2025, as the Effective Date of the TPPA.